LC 200

CHAMPION BUS INC. Pdf Download PDF Report

Dynamic Towing Test Data Form

Date 2007-06-18
Personnel S.C.
Temperature (°F) 74
Humidity (%) 85
Wind Direction W
Wind Speed (MPH) 8
Barometer (in.Hg) 30.1

Test Results

Inspect tow equipment-bus interface A safe and adequate connection was made between the tow equipment and the bus.
Inspect tow equipment-wrecker interface A safe and adequate connectin was made between the tow equipment and the wrecker.
Towing Comments A rear lift tow was performed incorporating a hydraulic under lift wrecker.
Description and location of any structural damage
General Comments No problems were encountered with the tow or towing interface.