1996 CHRYSLER ENTER VAN II

BRAUN CORPORATION Pdf Download PDF Report

Dynamic Towing Test Data Form

Date 1996-06-04
Personnel B.L.
Temperature (°F) 75
Humidity (%) 48
Wind Direction NW
Wind Speed (MPH) 5
Barometer (in.Hg) 30.03

Test Results

Inspect tow equipment-bus interface A safe and adequate connection was made between the tow equipment and bus.
Inspect tow equipment-wrecker interface A safe and adequate connection was made.
Towing Comments Tow was performed by means of a front lift tow with no problems noted.
Description and location of any structural damage None noted.
General Comments A lift of the front wheels was performed.