LFS-40

NOVA BUS Pdf Download PDF Report

Dynamic Towing Test Data Form

Date 2008-10-17
Personnel T.S.
Temperature (°F) 50
Humidity (%) 54
Wind Direction NE
Wind Speed (MPH) 6
Barometer (in.Hg) 30.14

Test Results

Inspect tow equipment-bus interface <p>A safe and adequate connection was made between the tow equipment and the bus.</p>
Inspect tow equipment-wrecker interface <p>A safe and adequate connection was made between the tow equipment and the wrecker.</p>
Towing Comments <p>A front lift tow was performed incorporating a hydraulic under lift wrecker.</p>
Description and location of any structural damage <p>None noted.</p>
General Comments <p>No problems with the tow or towing interface were encountered during the test.</p>