AC SERIES/CHALLENGER/DEFENDER/AMERICAN COACH

IC Bus/Champion Bus, Inc./General Coach American, Inc. Pdf Download PDF Report

Dynamic Towing Test Data Form

Date 2012-04-06
Personnel B.L. & K.D.
Temperature (°F) 44
Humidity (%) 39
Wind Direction N
Wind Speed (MPH) 6
Barometer (in.Hg) 30.06

Test Results

Inspect tow equipment-bus interface <p>A safe and adequate connection was made between the tow equipment and the bus.</p>
Inspect tow equipment-wrecker interface <p>A safe and adequate connection was made between the tow equipment and the wrecker</p>
Towing Comments <p>A front lift tow was performed incorporating a hydraulic under lift wrecker.</p>
Description and location of any structural damage <p>No damage or deformation was observed.</p>
General Comments <p>No problems with the towing interface or towing procedures were encountered.</p>