LOWFLOOR

GILLIG CORPORATION Pdf Download PDF Report

Dynamic Towing Test Data Form

Date 2004-12-02
Personnel S.C. & M.H.
Temperature (°F) 41
Humidity (%) 60
Wind Direction Calm
Wind Speed (MPH) Calm
Barometer (in.Hg) 30.12

Test Results

Inspect tow equipment-bus interface A safe and adequate connection was made between the tow equipment and the bus.
Inspect tow equipment-wrecker interface A safe and adequate connection was made between the tow equipment and the wrecker.
Towing Comments A front lift tow was performed incorporating a hydraulic under lift wrecker.
Description and location of any structural damage None noted.
General Comments The manufacturer does not recommend towing from the rear, therefore, a rear tow was not performed.